MEMO To: Production Staff From: Karen Mitchell, Operations Manager Date: September 4 Subject: Equipment Upgrade Schedule As announced last week, we will be replacing the packaging machines on Production Line B. The installation team from Nexgen Equipment will arrive on September 11. During the upgrade, Line B operations will be moved to Line C temporarily. Please check your work schedules and contact your supervisors if you have questions.
From: David Chen <d.chen@nexgen.com> To: Karen Mitchell <k.mitchell@brentford.com> Date: September 6 Subject: Installation Confirmation Dear Ms. Mitchell, This email confirms our team's arrival on September 11 at 7:00 A.M. The installation should be completed by the end of the day on September 12. Please ensure Line B is cleared by 6:30 A.M. on the first day. Our technicians will also provide a 2-hour training session for your staff on September 13. Best regards, David Chen Nexgen Equipment
BRENTFORD MANUFACTURING Line B Upgrade Schedule September 11 (Monday) - 7:00 A.M.: Installation team arrives - 8:00 A.M. - 5:00 P.M.: Old equipment removal September 12 (Tuesday) - 8:00 A.M. - 4:00 P.M.: New machine installation - 4:00 P.M. - 6:00 P.M.: Testing and calibration September 13 (Wednesday) - 9:00 A.M. - 11:00 A.M.: Staff training - 1:00 P.M.: Line B resumes normal operation
문항 1 / 5
안 푼 문항 5개
What is the purpose of the memo?
What does the email from Mr. Chen confirm?
According to the schedule, when will testing and calibration take place?
What is suggested about Production Line B?
Based on the email and the schedule, how long will the training session last?